Key Points
- Cambridgeshire County Council has confirmed a controlled pedestrian crossing outside Westwood Primary School in March.
- The estimated cost is £120,000, funded through the Local Transport Grant.
- Installation is targeted for the February half-term in 2027, subject to formal consultation and objections.
- The 21-day consultation is due to begin on November 25.
- The scheme follows earlier confusion over whether the crossing had been approved.
- Steve Barclay had campaigned for improved safety measures outside the school.
March (Cambridge Tribune) November 24, 2026 – Cambridgeshire County Council has confirmed plans for a new controlled pedestrian crossing outside Westwood Primary School in March. The approximately £120,000 scheme is intended to improve safety for pupils, parents and carers travelling between the school’s two sites on Maple Grove. A formal 21-day consultation is scheduled to begin on November 25, with construction targeted for the February half-term in 2027, subject to objections and the completion of the necessary process.
- Key Points
- Why has a pedestrian crossing been confirmed outside Westwood Primary School?
- When will the consultation and construction take place?
- What did Alex Beckett and Steve Barclay say about the scheme?
- What is the background to the Westwood Primary School crossing?
- How could the crossing affect pupils, families and local residents?
Why has a pedestrian crossing been confirmed outside Westwood Primary School?
Cambridgeshire County Council said the crossing would make it safer and easier for children and families to walk between Westwood Primary School’s two sites, which are located on opposite sides of Maple Grove.
The council said school drop-off and pick-up periods create additional congestion on the busy road. It added that councillors unanimously supported a motion in July calling for proposals for a new controlled crossing after local concerns about road safety and accessibility.
The council said the selected proposal is intended to provide the greatest overall benefit to pupils, parents and carers while minimising the loss of potential parking spaces. The scheme has received positive stakeholder feedback, according to the council.
When will the consultation and construction take place?
The formal consultation is due to start on November 25 and will run for 21 days. Construction is targeted for the February half-term in 2027, although the timetable remains subject to any objections and the completion of the approval process.
The council said the estimated cost is around £120,000 and will be funded through its Local Transport Grant allocation. Funding became available for the scheme after a delay affecting another crossing allowed money to be reallocated.
What did Alex Beckett and Steve Barclay say about the scheme?
Alex Beckett, chair of Cambridgeshire County Council’s Highways and Transport Committee, said there had been confusion about the delivery timetable and that the latest announcement was intended to provide certainty for the local community.
Beckett said the council had originally expected to seek funding through its capital prioritisation process in the new year. He said the reallocated funding meant the crossing could be delivered earlier, subject to objections.
Steve Barclay, the Conservative Member of Parliament for North East Cambridgeshire, had launched a campaign for safety measures outside the school. The development follows earlier disagreement over council documents that appeared to state the crossing would be delivered before officers later indicated that it had not been formally agreed.
That discrepancy led Barclay to call for an investigation into accountability. The council has now confirmed the scheme, its estimated cost and the intended delivery period.
What is the background to the Westwood Primary School crossing?
Earlier proposals for pelican crossings and flashing speed-limit signs outside Westwood Primary School were rejected in March after council officers cited injury-accident thresholds. The school’s two sites remain separated by Maple Grove, where traffic and congestion are particular concerns during school arrival and collection times. In July, councillors supported a motion calling for new crossing proposals and funding to be brought forward. The council subsequently selected a controlled crossing design and confirmed that funding could be transferred to support delivery.
How could the crossing affect pupils, families and local residents?
If delivered as planned, the crossing could provide a designated route between the school sites and improve access for children, parents and carers walking to school. It could also help families cross Maple Grove during busy periods, although the consultation may lead to changes or objections before construction begins. The scheme is intended to support the council’s wider aim of making active travel safer and more accessible. Local residents will have an opportunity to respond during the 21-day consultation.