Key Points
- Cambridge City Council has approved an £89.4 million Civic Quarter programme.
- Sir Robert McAlpine is the preferred contractor for work on the Guildhall, Corn Exchange and Market Square.
- Enabling works are scheduled to begin in January 2027.
- The programme is expected to be completed in stages by summer 2029.
- The council expects the investment to break even over 30 years, mainly through income from the improved sites.
Cambridge (Cambridge Tribune) November 27, 2026 – Sir Robert McAlpine is set to begin enabling works in January 2027 on Cambridge City Council’s £89.4 million Civic Quarter redevelopment. The programme will upgrade the Guildhall, Corn Exchange, Market Square and associated public spaces. Councillors approved the scheme on November 26, with completion planned for summer 2029. The project aims to improve the historic sites’ accessibility, sustainability and long-term financial performance.
- Key Points
- When will Sir Robert McAlpine start the Cambridge Civic Quarter project?
- What will the £89.4 million Cambridge revamp include?
- What have Cambridge officials and Sir Robert McAlpine said?
- What is the background to the Cambridge Civic Quarter development?
- How could the project affect Cambridge residents, traders and visitors?
When will Sir Robert McAlpine start the Cambridge Civic Quarter project?
According to Cambridge City Council’s approved programme, enabling works are due to start in January 2027. The council’s published documents identify Sir Robert McAlpine as the preferred contractor, following its selection in May 2025 and appointment under a pre-construction services agreement in June 2025.
The initial phase will prepare the sites for construction. The Guildhall’s final events are scheduled for the end of December 2026, while the Corn Exchange is expected to move out by mid-January 2027. Market traders are expected to move to temporary stalls from March 2027 at the earliest.
What will the £89.4 million Cambridge revamp include?
The work covers three major civic assets: the Guildhall, Corn Exchange and Market Square. Cambridge City Council said the programme is intended to protect the historic buildings, improve public access and create more welcoming public spaces.
The timetable published in council documents indicates that the Market Square could be completed by March 2028, the Corn Exchange could reopen in summer 2028 and the Guildhall could be finished by December 2028. Public-space works are scheduled to continue until August 2029.
The council expects to retain ownership of the three assets and break even over 30 years, with income generated by the improvements forming the main source of repayment. Earlier council documents recorded higher detailed cost estimates, including approximately £109.4 million in August 2026, while the approved programme was presented with an £89.4 million investment figure.
What have Cambridge officials and Sir Robert McAlpine said?
Cambridge City Council Leader Councillor Katie Thornburrow said the Guildhall, Corn Exchange and Market Square required major work to continue serving the city. She said the council expected the investment to break even over 30 years while retaining ownership of the assets.
“The adaptive reuse and conservation of these assets will enable new life to be breathed into the Guildhall, for the Market Square to be a cultural focus and for the Corn Exchange to better serve as East Anglia’s premier concert venue,” said Mike Coleman, Operations Director, Special Projects, Sir Robert McAlpine.
The council’s decision allows the programme to proceed within the approved budget and enables preparations for construction, including design development, procurement, decant planning and stakeholder engagement.
What is the background to the Cambridge Civic Quarter development?
The Civic Quarter programme brings together improvements to the Guildhall, Corn Exchange, Market Square and surrounding public realm. Sir Robert McAlpine was selected as preferred contractor in May 2025 and began early contractor involvement the following month. Council reports said work would start in January 2027 and take two to three years. The Full Council approved the programme on November 26, 2026, after earlier Cabinet recommendations and scrutiny of the scheme’s costs and delivery options.
How could the project affect Cambridge residents, traders and visitors?
The project is expected to cause phased changes to access, events, trading arrangements and public-space use while construction takes place. Residents and visitors may see temporary disruption around the three sites, while traders are expected to use temporary stalls during part of the Market Square works.
Once completed, the programme is intended to provide a refurbished Guildhall, an improved concert venue at the Corn Exchange and a redesigned Market Square. The council’s plan links the investment to income from the sites, meaning the project’s long-term financial performance will depend partly on how effectively the improved venues and spaces are used.